Friday 29th May. The tilers started working on getting our bare concret floors covered with some tiles. They asked to meet one of us at the site at 7am to discuss where we wanted our tiles....so surprise surprise Rachel wanted to go down to see the "Tradies"...and from all accounts from Rachel, she wasnt disapointed. The boys will be back next week to grout the tiles...will have to make sure she is at work.
Saturday, May 31, 2008
BLOKES WORLD - Part 2
Saturday, May 24, 2008
BLOKES WORLD - The Shed Part 1
The Guys at Precision Steel Frames came up with the best quote for our 6m x 12m shed. We have a 2 bay car port (6x6m) and a 6 x 6m storage (I mean beer drinking area). These photos show the first the first day of construction. Thanks to Jason Spies (The Shed Builder) and the guys at Goombungee Concreting for the work so far. Hoepfully some time next week we will have a place to put the landscaping equipment.
Thursday, May 22, 2008
Cannot get inside - So lets start outside
21st May - We decided that we would start to plant some shrubs outside and get some tube stock established in the garden ready for our move into the house. We ordered some Pittosporum tenuifolium "Silver Sheen" tube stock from Fernview Nurseries in Melbourne. The stock was packaged and sent via Aust Post and arrived in great condition. We got our mate Davo from Davos Bob Cat hire in Highfields to dig a trench to loosen up some soil to help the roots sprout and secure them in the ground. Brought 30m of poly pipe and some drippers for watering once the tank and pump are hooked up. We are very happy with the outcome.
Shelving and Doors
Tuesday, May 13, 2008
At Lock Up
Cabinets and Kitchen are In
Thursday, May 8, 2008
Now for the Bricks
Thursday 7th May and the brickies turn up in force to start the work. We chose a Boral double height brick called Sandstone Gold. They finshed the side along the kids rooms and left hand front after day one. A great finish with the light mortar. The colour of the window frames and the front door really sets the brick tone as great match.
Monday, May 5, 2008
Plaster Is Up - A Whole New Look
Stone, Stones and more Rock
Problem # One. We knew we had to put up a retainer wall of some description, but when the guy came in to do the cut for the retainer wall we struck rock and made it impossible to dig any further down for the posts for a timber retainer. Solution....build a rock wall. Mmmmm easier said than done. But none the less a good outcome. Mark Davies at Davos Bobcat Hire (0418 193 727) did a fantasic job on the wall.
The Timber Facier
Day 11 - The Complete Frame
2 days of work and the frame work is completed. At the end of this day the Rhino Wrap arrived and was put on the next day. On that same day the Colourbond steel roof material arrived. We thought it would be days before the roofers would start but guess what...Day 13 and they were starting, at the end of day 16 the roof was complete.
Day 9 - The Framing Starts
Next came the concrete